
With the average Ledite block weighing approx. 70 lbs., Atomic has developed several mechanisms to facilitate block installation, increase worker safety and dramatically increase the number of block that can be installed per shift.
An air operated lifting unit is available that is easily handled by one man and can lift three blocks automatically. This innovative unit greatly speeds the laying of block while protecting workers from the strain of excessive lifting.
To further speed installation and protect workers, Atomic has developed a fully-automated computer-controlled robot. This hands-free unit quickly and accurately places block at speeds of up to 20,000 block per shift. The system ensures proper alignment and level while eliminating manual block handling.

Newly poured concrete floors or foundations must be cured and capable of supporting formlift and palletized block - combined load total. Reasonable access to the site must be provided. Reasonable access assumes palletized Ledite block material weighing approximately 4,000 lbs. each, with skid dimensions of 48" x 48" x 30"-H, may be transported through corridors, doorways, elevators, etc. using conventional material handling (carts, electric pallet lift, forklift, etc.) equipment as necessary.
Access routing may require pallets be transported through hospital corridors utilizing propane or electric powered handling equipment. All existing pipes, ductwork, electrical conduits, clips and other items above or around the Ledite vault area must be removed. Where existing beams or columns fall within the shielding ceiling or walls, all fireproofing materials must be removed to allow proper grouting around beams to maintain shielding integrity.
Customer is responsible for pre-delivery inspection of construction zone and for providing:

Reasonable access to the site must be provided. Materials needed for the first two weeks of installation must be located on site in close proximity to the vault construction area. Pallets will be shuttled from the storage area to the respective room footprints as needed. Single pallets of block may be set at ground level, or at each staged scaffolded area as needed. A 10' area (minimum) around the accelerator room footprint must be maintained throughout the course of installation. This area is used for pallet storage, scaffold setup, etc.
There are five methods of handling Ledite block:
1. Atomic Automated Robot
2. Mechanically (ARM)
3. Hand lifting half sized block
4. Two man lifting
5. Single man lifting w/proper safety protection

Walls are constructed of multiple layers of Ledite block, a lift of blocks approximately 1200 mm high will be laid to a bunker, then appropriately designed scaffold will be erected within the footprint of the bunker. Once the scaffold is handed over, the next 1200 mm high lift of blocks will be installed. This sequence will continue until the bearing plate level for the roof steelwork has been reached. Bearing plates will be grouted in with high density grout and left to cure for 24 hours.
Block will be laid in a running bond pattern with staggered seams between each respective wythe of block. At the first course, a center bond beam must also be poured in place. This high-density grouted bond beam shall consist of steel reinforcing bar laid in accordance with installation drawings with grout materials placed and properly compacted. Bond beam sections shall require a minimum 24-hour curing period before erecting additional block above.
Once the bearing plate level has been reached, additional bond beams with steel embedded bearing plates shall be constructed.
Upon attaining the block elevation at which the bearing plates are to be installed, the second wythe of block from the inside of the room shall be left devoid of all block. That area forms the upper horizontal bond beam. Within this upper horizontal bond beam, #6 rebar is to be installed in the same manner and to the same requirement as in the lower bond beam. All bearing plates are to be installed solidly in Ledite grout bond beams. Bearing plates are to be installed level on both axes and perpendicular to the beams. All bearing plate elevations are to be within 1/16" of the elevation specified on Atomic's installation drawings. All bearing plate elevations are to be verified with a laser level.
The shielding of the mechanical penetrations opening is critical to the total overall shielding of the project. It is important that the shielding material be installed so that no gaps exist between the shielding materials. At the top of the mechanical penetrations opening (also termed the duct opening), a steel header lintel is installed. Usually, this header lintel is a steel channel that is installed with the flat side of the channel downward. The upper section of the channel then becomes the form into which Ledite grout and Ledite block is installed.

Structural steelwork will then be installed spanning between bearing plates on opposites of bunker walls. One to three steel beams will be placed at correct positions starting from sidewall. Beam(s) will then be loaded with appropriate block thickness as called for on drawings. This process of setting beams and loading with block will then be repeated until the entire ceiling has been properly constructed and shielding installed. Once steel beams have been installed per drawings, they will be tack welded to bearing plates to hold them in position.

After walls and ceiling have been erected, the radiation shield door, motor drive and associated components shall be installed. The door finish frame is welded to the sub-frame after all Ledite block work is complete. The door is raised by first setting it on a door dolly and then hoisting it into place using a beam clamp in conjunction with a chain hoist.
After the door has been installed, the motor drive and associated components as specified (i.e. pushbuttons, safety edges, etc. ) for the project are to be installed.
As soon as the accelerator is able to produce a radiation beam, a survey shall be conducted by a qualified radiation expert.
The main objective of the Initial Radiation Area Survey (IRAS) is to:
After the IRAS is conducted and the results interpreted, Atomic will discuss the survey with the client or client's appointed representative. If it is found that any areas are questionable, additional surveys may be required to determine cause of high reading or better quantify values, extent or location of high readings. If, after review and consultation with the client and Atomic, it is agreed that additional shielding or rearrangement of shielding or baffles may be required, Atomic shall be provided the necessary time and opportunity to reasonably address any areas. Additionally, time must be allocated to acquire any additional shielding as may be required.
It is suggested that finishes not be installed outside the accelerator room until the initial radiation survey can be conducted.
A final radiation area survey shall be conducted after all remedial work has been completed as may be required.
After the final radiation area survey, a final written report will be provided indicating maximum survey results obtained outside occupiable barriers. It is the customer's responsibility to obtain all necessary operating licenses, inspections, etc. as may be required. Any survey reports, facility operation logs, etc. are the responsibility of the customer. The owner appointed radiological health physicist is responsible to ensure that all areas which may be reasonable accessible or occupied by workers or general public must be safe and meet all applicable governing regulations.